Training Name | Training Provider | Duration | Date Completed | Verified by RSA Panel | |
Continued Professional Development – Road Safety Audit Practice (Senior Auditor) | Main Roads WA / IPWEA | 2 days | 28/10/2024 | ✔ | |
Road Safety Engineering | MRWA/IPWEA | 2 days | 29/08/2020 | ✔ |
Date of Audit | Location Type | Stage of Audit | Project Type | Details |
15/07/2024 | Section | Pre/Post opening | Public Transport Project Major | More Details... |
04/12/2023 | Section | Road Safety Inspection | Public Transport Project Major | More Details... |
30/06/2023 | Section | Preliminary Design | Public Transport Project Minor | More Details... |
30/06/2023 | Section | Preliminary Design | Public Transport Project Minor | More Details... |
30/06/2023 | Section | Road Safety Inspection | Public Transport Project Minor | More Details... |
20/04/2023 | Section | Pre/Post opening | Shared use Facilities | More Details... |
12/04/2023 | Intersection | Pre/Post opening | Grade Separation | More Details... |
16/03/2023 | Intersection | Pre/Post opening | Grade Separation | More Details... |
19/12/2022 | Intersection | Preliminary Design | Intersection Improvements Minor | More Details... |
16/12/2022 | Intersection | Feasibility | Road Safety Inspection – Intersection | More Details... |
12/12/2022 | Point | Preliminary Design | Public Transport Project Minor | More Details... |
12/12/2022 | Point | Feasibility | Road Safety Inspection – Intersection | More Details... |
12/12/2022 | Intersection | Feasibility | Road Safety Inspection – Intersection | More Details... |
24/05/2021 | Section | Preliminary Design | Urban Road Upgrade | More Details... |
31/01/2022 | Section | Preliminary Design | Rural Road Upgrade | More Details... |
31/01/2022 | Section | Preliminary Design | Rural Road Upgrade | More Details... |
31/01/2022 | Section | Preliminary Design | Rural Road Upgrade | More Details... |
31/01/2022 | Section | Preliminary Design | Rural Road Upgrade | More Details... |
31/01/2022 | Section | Preliminary Design | Rural Road Upgrade | More Details... |
31/01/2022 | Section | Preliminary Design | Rural Road Upgrade | More Details... |
31/01/2022 | Section | Preliminary Design | Rural Road Upgrade | More Details... |
31/01/2022 | Section | Preliminary Design | Rural Road Upgrade | More Details... |
31/01/2022 | Section | Preliminary Design | Rural Road Upgrade | More Details... |
31/01/2022 | Section | Preliminary Design | Rural Road Upgrade | More Details... |
24/01/2022 | Section | Detailed Design | Rural Route Treatment | More Details... |
08/02/2022 | Point | Preliminary Design | Rural Route Treatment | More Details... |
14/01/2022 | Section | Detailed Design | Rural Route Treatment | More Details... |
12/01/2022 | Section | Detailed Design | Rural Road Upgrade | More Details... |
28/04/2020 | Section | Detailed Design | Rural Road Upgrade | More Details... |
16/09/2019 | Section | Road Safety Inspection | Urban Road Upgrade | More Details... |
24/09/2019 | Section | Road Safety Inspection | Urban Road Upgrade | More Details... |
22/08/2019 | Section | Pre/Post opening | Urban Road Upgrade | More Details... |
08/11/2019 | Section | Road Safety Inspection | Urban Road Upgrade | More Details... |
16/08/2019 | Section | Road Safety Inspection | Urban Road Upgrade | More Details... |
06/02/2020 | Section | Detailed Design | Cycling Facilities | More Details... |
12/02/2020 | Section | Pre/Post opening | Cycling Facilities | More Details... |
19/03/2019 | Point | Road Safety Inspection | Pedestrian Facilities | More Details... |
18/01/2019 | Section | Detailed Design | Rural Route Treatment | More Details... |
11/11/2019 | Section | Preliminary Design | Cycling Facilities | More Details... |
09/06/2018 | Section | Detailed Design | Rural Road Upgrade | More Details... |
19/04/2018 | Intersection | Detailed Design | Land Use Development | More Details... |
20/08/2018 | Intersection | Detailed Design | Rural Road Upgrade | More Details... |
11/05/2018 | Intersection | Detailed Design | New roundabout | More Details... |
18/01/2019 | Section | Detailed Design | Rural Route Treatment | More Details... |
09/11/2018 | Intersection | Detailed Design | Urban Road Upgrade | More Details... |
03/08/2017 | Section | Detailed Design | Rural Road Upgrade | More Details... |
08/08/2017 | Section | Detailed Design | Rural Road Upgrade | More Details... |
23/06/2017 | Intersection | Road Safety Inspection | Road Safety Inspection – Intersection | More Details... |
26/04/2017 | Point | Detailed Design | Land Use Development | More Details... |
06/12/2016 | Section | Detailed Design | Land Use Development | More Details... |
12/10/2017 | Intersection | Detailed Design | Land Use Development | More Details... |
27/10/2017 | Section | Detailed Design | Rural Road Upgrade | More Details... |
12/11/2017 | Intersection | Detailed Design | Land Use Development | More Details... |
14/12/2016 | Section | Pre/Post opening | Public Transport Project Major | More Details... |
18/05/2016 | Section | Detailed Design | Public Transport Project Major | More Details... |
29/08/2016 | Section | Detailed Design | Land Use Development | More Details... |
06/12/2016 | Section | Detailed Design | Land Use Development | More Details... |
15/12/2016 | Section | Road Safety Inspection | Urban Road Upgrade | More Details... |
08/12/2016 | Section | Pre/Post opening | Urban Road Upgrade | More Details... |
06/11/2015 | Section | Detailed Design | Urban Road Upgrade | More Details... |
08/12/2016 | Section | Road Safety Inspection | Rural Road Upgrade | More Details... |
25/10/2016 | Section | Pre/Post opening | Rural Road Upgrade | More Details... |
06/11/2015 | Section | Detailed Design | Urban Road Upgrade | More Details... |
14/06/2016 | Section | Detailed Design | Rural Road Upgrade | More Details... |
09/06/2016 | Point | Feasibility | Rural Road Upgrade | More Details... |
26/05/2016 | Intersection | Road Safety Inspection | Unsignalised Intersection | More Details... |
25/06/2015 | Intersection | Road Safety Inspection | Road Safety Inspection – Intersection | More Details... |
21/12/2015 | Point | Road Safety Inspection | Unsignalised Intersection | More Details... |
28/05/2015 | Intersection | Preliminary Design | Urban Road Upgrade | More Details... |
26/03/2014 | Intersection | Road Safety Inspection | Local Traffic Management Project | More Details... |
Current 5 Years | |||||
---|---|---|---|---|---|
Project Type | Feasibility | Preliminary Design | Detailed Design | Pre/Post opening | Road Safety Inspection |
Blackspot project | - | - | - | - | - |
Cycling Facilities | - | - | - | 1 | - |
Grade Separation | - | - | - | 2 | - |
Intersection Improvements Major | - | - | - | - | - |
Intersection Improvements Minor | - | 1 | - | - | - |
Land Use Development | - | - | - | - | - |
Local Traffic Management Project | - | - | - | - | - |
New Road Project | - | - | - | - | - |
New roundabout | - | - | - | - | - |
Pedestrian Facilities | - | - | - | - | - |
Public Transport Project Major | - | - | - | 1 | 1 |
Public Transport Project Minor | - | 3 | - | - | 1 |
Road Safety Inspection – Intersection | 3 | - | - | - | - |
Road Safety Inspection – Route | - | - | - | - | - |
Rural Road Upgrade | - | 10 | 2 | - | - |
Rural Route Treatment | - | 1 | 2 | - | - |
Safety Barrier Project | - | - | - | - | - |
Shared use Facilities | - | - | - | 1 | - |
Signalised Intersection | - | - | - | - | - |
Streetscape Works | - | - | - | - | - |
Traffic Calming | - | - | - | - | - |
Unsignalised Intersection | - | - | - | - | - |
Urban Road Upgrade | - | 1 | - | - | - |
Urban Route Treatment | - | - | - | - | - |
Totals | 3 | 16 | 4 | 5 | 2 |
Current 10 Years | |||||
---|---|---|---|---|---|
Project Type | Feasibility | Preliminary Design | Detailed Design | Pre/Post opening | Road Safety Inspection |
Blackspot project | - | - | - | - | - |
Cycling Facilities | - | 1 | 1 | 1 | - |
Grade Separation | - | - | - | 2 | - |
Intersection Improvements Major | - | - | - | - | - |
Intersection Improvements Minor | - | 1 | - | - | - |
Land Use Development | - | - | 7 | - | - |
Local Traffic Management Project | - | - | - | - | - |
New Road Project | - | - | - | - | - |
New roundabout | - | - | 1 | - | - |
Pedestrian Facilities | - | - | - | - | 1 |
Public Transport Project Major | - | - | 1 | 2 | 1 |
Public Transport Project Minor | - | 3 | - | - | 1 |
Road Safety Inspection – Intersection | 3 | - | - | - | 2 |
Road Safety Inspection – Route | - | - | - | - | - |
Rural Road Upgrade | 1 | 10 | 8 | 1 | 1 |
Rural Route Treatment | - | 1 | 4 | - | - |
Safety Barrier Project | - | - | - | - | - |
Shared use Facilities | - | - | - | 1 | - |
Signalised Intersection | - | - | - | - | - |
Streetscape Works | - | - | - | - | - |
Traffic Calming | - | - | - | - | - |
Unsignalised Intersection | - | - | - | - | 2 |
Urban Road Upgrade | - | 2 | 3 | 2 | 5 |
Urban Route Treatment | - | - | - | - | - |
Totals | 4 | 18 | 25 | 9 | 13 |
Current 5 Years | |||||
---|---|---|---|---|---|
Project Type | Feasibility | Preliminary Design | Detailed Design | Pre/Post opening | Road Safety Inspection |
Blackspot project | - | - | - | - | - |
Cycling Facilities | - | - | - | - | - |
Grade Separation | - | - | - | - | - |
Intersection Improvements Major | - | - | 1 | - | - |
Intersection Improvements Minor | - | - | 1 | - | - |
Land Use Development | - | 1 | - | - | - |
Local Traffic Management Project | - | - | - | - | - |
New Road Project | - | - | - | - | - |
New roundabout | - | 1 | - | 2 | - |
Pedestrian Facilities | - | - | - | 1 | - |
Public Transport Project Major | - | 1 | 2 | 1 | - |
Public Transport Project Minor | - | - | - | - | - |
Road Safety Inspection – Intersection | - | - | - | - | - |
Road Safety Inspection – Route | - | - | - | - | 5 |
Rural Road Upgrade | - | - | 1 | - | - |
Rural Route Treatment | - | - | - | - | - |
Safety Barrier Project | - | - | - | 1 | - |
Shared use Facilities | - | - | - | - | - |
Signalised Intersection | - | - | - | - | - |
Streetscape Works | - | - | - | - | - |
Traffic Calming | - | - | - | - | - |
Unsignalised Intersection | - | - | - | - | - |
Urban Road Upgrade | - | 1 | - | - | - |
Urban Route Treatment | - | - | - | - | - |
Totals | 0 | 4 | 5 | 5 | 5 |
Current 10 Years | |||||
---|---|---|---|---|---|
Project Type | Feasibility | Preliminary Design | Detailed Design | Pre/Post opening | Road Safety Inspection |
Blackspot project | - | - | - | - | 2 |
Cycling Facilities | - | - | 2 | - | - |
Grade Separation | - | - | - | - | - |
Intersection Improvements Major | - | 1 | 11 | - | - |
Intersection Improvements Minor | - | - | 2 | - | - |
Land Use Development | - | 1 | 11 | 3 | 3 |
Local Traffic Management Project | - | - | - | - | - |
New Road Project | - | - | 1 | - | - |
New roundabout | - | 1 | 5 | 2 | - |
Pedestrian Facilities | - | - | 1 | 1 | - |
Public Transport Project Major | - | 3 | 6 | 1 | - |
Public Transport Project Minor | - | - | - | - | - |
Road Safety Inspection – Intersection | - | - | - | - | 19 |
Road Safety Inspection – Route | - | - | - | - | 12 |
Rural Road Upgrade | - | - | 12 | - | - |
Rural Route Treatment | - | 3 | 2 | - | - |
Safety Barrier Project | - | - | - | 1 | - |
Shared use Facilities | - | 1 | - | - | - |
Signalised Intersection | - | - | - | - | - |
Streetscape Works | - | - | - | - | - |
Traffic Calming | - | - | - | - | - |
Unsignalised Intersection | - | - | - | 1 | - |
Urban Road Upgrade | - | 5 | 4 | - | - |
Urban Route Treatment | - | - | - | - | - |
1 | |||||
Totals | 0 | 16 | 57 | 9 | 36 |