Training Name | Training Provider | Duration | Date Completed | Verified by RSA Panel | |
Crash Map Practical Application Training | Main Roads WA-Road Safety Branch | 1 day | 28/02/2023 | ✔ | |
Roadside Design | Main Roads, WA | 2 days | 06/07/2017 | ✔ | |
Advanced Worksite Traffic Management | Kelyn Training Services | 5 days | 04/12/2020 | ✔ | |
Continuing Professional Development | IPWEA and Main Roads | 2 days | 26/03/2021 | ✔ | |
Road Safety Engineering | IPWEA | 2 days | 02/07/2020 | ✔ |
Date of Audit | Location Type | Stage of Audit | Project Type | Details |
10/10/2024 | Intersection | Pre/Post opening | Blackspot project | More Details... |
11/11/2024 | Intersection | Road Safety Inspection | Road Safety Inspection – Intersection | More Details... |
25/09/2024 | Intersection | Pre/Post opening | Intersection Improvements Major | More Details... |
24/07/2024 | Section | Pre/Post opening | Blackspot project | More Details... |
24/07/2024 | Intersection | Detailed Design | Intersection Improvements Minor | More Details... |
Current 5 Years | |||||
---|---|---|---|---|---|
Project Type | Feasibility | Preliminary Design | Detailed Design | Pre/Post opening | Road Safety Inspection |
Blackspot project | - | - | - | 2 | - |
Cycling Facilities | - | - | - | - | - |
Grade Separation | - | - | - | - | - |
Intersection Improvements Major | - | - | - | 2 | - |
Intersection Improvements Minor | - | - | 1 | - | - |
Land Use Development | - | - | - | - | - |
Local Traffic Management Project | - | - | - | - | - |
New Road Project | - | - | - | - | - |
New roundabout | - | - | - | - | - |
Pedestrian Facilities | - | - | - | - | - |
Public Transport Project Major | - | - | - | - | - |
Public Transport Project Minor | - | - | - | - | - |
Road Safety Inspection – Intersection | - | - | - | - | 1 |
Road Safety Inspection – Route | - | - | - | - | - |
Rural Road Upgrade | - | - | - | - | - |
Rural Route Treatment | - | - | - | - | - |
Safety Barrier Project | - | - | - | - | - |
Shared use Facilities | - | - | 1 | - | - |
Signalised Intersection | - | - | - | - | - |
Streetscape Works | - | - | - | - | - |
Traffic Calming | - | - | - | - | - |
Unsignalised Intersection | - | - | - | - | - |
Urban Road Upgrade | - | - | - | - | - |
Urban Route Treatment | - | - | - | - | - |
Totals | 0 | 0 | 2 | 4 | 1 |
Current 10 Years | |||||
---|---|---|---|---|---|
Project Type | Feasibility | Preliminary Design | Detailed Design | Pre/Post opening | Road Safety Inspection |
Blackspot project | - | - | - | 2 | - |
Cycling Facilities | - | - | - | - | - |
Grade Separation | - | - | - | - | - |
Intersection Improvements Major | - | - | - | 2 | - |
Intersection Improvements Minor | - | - | 1 | - | - |
Land Use Development | - | - | - | - | - |
Local Traffic Management Project | - | - | - | - | - |
New Road Project | - | - | - | - | - |
New roundabout | - | - | - | - | - |
Pedestrian Facilities | - | - | - | - | - |
Public Transport Project Major | - | - | - | - | - |
Public Transport Project Minor | - | - | - | - | - |
Road Safety Inspection – Intersection | - | - | - | - | 1 |
Road Safety Inspection – Route | - | - | - | - | - |
Rural Road Upgrade | - | - | - | - | - |
Rural Route Treatment | - | - | - | - | - |
Safety Barrier Project | - | - | - | - | - |
Shared use Facilities | - | - | 1 | - | - |
Signalised Intersection | - | - | - | - | - |
Streetscape Works | - | - | - | - | - |
Traffic Calming | - | - | - | - | - |
Unsignalised Intersection | - | - | - | - | - |
Urban Road Upgrade | - | - | - | - | - |
Urban Route Treatment | - | - | - | - | - |
Totals | 0 | 0 | 2 | 4 | 1 |
Current 5 Years | |||||
---|---|---|---|---|---|
Project Type | Feasibility | Preliminary Design | Detailed Design | Pre/Post opening | Road Safety Inspection |
Blackspot project | - | - | 4 | 2 | 3 |
Cycling Facilities | - | - | - | - | - |
Grade Separation | - | - | - | - | - |
Intersection Improvements Major | - | - | 2 | 1 | - |
Intersection Improvements Minor | - | - | - | - | - |
Land Use Development | - | - | - | - | - |
Local Traffic Management Project | - | - | - | - | - |
New Road Project | - | - | - | - | - |
New roundabout | - | - | 1 | - | - |
Pedestrian Facilities | - | - | - | - | - |
Public Transport Project Major | - | - | - | - | - |
Public Transport Project Minor | - | - | - | - | - |
Road Safety Inspection – Intersection | - | - | - | - | 16 |
Road Safety Inspection – Route | - | - | - | - | 3 |
Rural Road Upgrade | 1 | 9 | 2 | - | - |
Rural Route Treatment | - | 1 | 2 | - | - |
Safety Barrier Project | - | - | - | - | - |
Shared use Facilities | - | - | 1 | - | - |
Signalised Intersection | - | - | 1 | - | - |
Streetscape Works | - | - | - | - | - |
Traffic Calming | - | - | - | - | - |
Unsignalised Intersection | - | - | - | - | - |
Urban Road Upgrade | - | - | - | - | - |
Urban Route Treatment | - | - | - | - | - |
Totals | 1 | 10 | 13 | 3 | 22 |
Current 10 Years | |||||
---|---|---|---|---|---|
Project Type | Feasibility | Preliminary Design | Detailed Design | Pre/Post opening | Road Safety Inspection |
Blackspot project | - | - | 4 | 2 | 5 |
Cycling Facilities | - | - | - | - | - |
Grade Separation | - | - | - | - | - |
Intersection Improvements Major | - | - | 2 | 1 | - |
Intersection Improvements Minor | - | - | - | - | - |
Land Use Development | - | - | - | - | - |
Local Traffic Management Project | - | - | - | - | - |
New Road Project | - | - | 1 | - | - |
New roundabout | - | - | 1 | - | - |
Pedestrian Facilities | - | - | - | - | - |
Public Transport Project Major | - | - | - | - | - |
Public Transport Project Minor | - | - | - | - | - |
Road Safety Inspection – Intersection | - | - | - | - | 16 |
Road Safety Inspection – Route | - | - | - | - | 3 |
Rural Road Upgrade | 1 | 9 | 6 | - | - |
Rural Route Treatment | - | 1 | 2 | - | - |
Safety Barrier Project | - | - | - | - | - |
Shared use Facilities | - | - | 1 | - | - |
Signalised Intersection | - | - | 1 | - | - |
Streetscape Works | - | - | - | - | - |
Traffic Calming | - | - | - | - | - |
Unsignalised Intersection | - | - | - | - | - |
Urban Road Upgrade | - | - | - | - | - |
Urban Route Treatment | - | - | - | - | - |
Totals | 1 | 10 | 18 | 3 | 24 |